Re-planning schedule and costs on the Balimed Denpasar hospital building development project

  • Eka Wahyuni Department of Civil Engineering, Universitas Warmadewa, Denpasar, Indonesia
  • I Wayan Jawat Department of Civil Engineering, Universitas Warmadewa, Denpasar, Indonesia
  • Ni Made Widya Pratiwi Department of Civil Engineering, Universitas Warmadewa, Denpasar, Indonesia

Abstrak

In this study, a re-planning of schedules and costs will be carried out on the Balimed Denpasar Hospital Building Development Project which aims to be a basis for decision making so that the project runs according to plan. The calculation results obtained a Schedule Performance Index (SPI) of 0,683 and a Cost Performance Index (CPI) of 1 which shows that the project implementation was completed late with the budget as planned. If the project performance at the time of reporting remains the same until the rest of the work is completed, then the amount of the Estimate All Cost (EAC) is IDR. 46.881.134.933,39, which is the same amount as planned. This shows that there is no additional cost, so the total cost of remaining work is IDR. 40.249.362.635,43. The implementation time increased by 183 days because the Estimate All Schedule (EAS) was longer, which was 723 days from the original plan of 540 days.

Referensi

Sugiyanto, Manajemen Pengendalian Proyek. Surabaya: Scopindo Media Pustaka, 2020.

H. Ashad, L. B. Said, and U. D. Hardi, “Penerapan Metode Analisis Nilai Hasil terhadap Biaya dan Waktu Pelaksanaan Proyek (Studi Kasus Pembangunan ATC Tower Bandar Udara Syukuran Aminuddin Amir, Di Luwuk),†Ge-STRAM J. Perenc. dan Rekayasa Sipil, vol. 3, no. 2, pp. 101–110, 2020.

M. Girish, A. Gaddam, and A. B. Landage, “A Review on Earned Value Management and Earned Schedule Method for Construction Project,†no. July, 2022.

N. Sakinah, “Akselerasi : Jurnal Ilmiah Teknik Sipil Akselerasi : Jurnal Ilmiah Teknik Sipil,†J. Ilm. Tek. Sipil, vol. 3, no. 1, pp. 63–69, 2021.

D. Asmaroni and A. Setiawan, “Penggunaan Metode Nilai Hasil (Earned Value Analysis) Terhadap Biaya Dan Waktu Pada Proyek Konstruksi Bangunan Perumahan (Studi Kasus Proyek Konstruksi Bangunan Perumahan PT. Graha Praja Kencana Di Desa Ceguk Kecamatan Tlanakan Kabupaten Pamekasan),†Ge-STRAM J. Perenc. dan Rekayasa Sipil, vol. 3, no. 1, pp. 31–39, 2020, doi: 10.25139/jprs.v3i1.2439.

W. Kurniawan, D. Purnomo, and Astuti, “Analisis Earned Value Waktu dan Biaya Proyek Konstruksi Jalan,†J. Saintis, vol. 17, no. 2, pp. 6–16, 2017.

D. K. Sudarsana, “Pengendalian Biaya dan Jadual Terpadu pada Proyek Konstruksi,†J. Ilm. Tek. Sipil, vol. 12, no. 2, pp. 117–125, 2008.

Y. Sutomo, S. Anwar, M. Eng, and A. Firmanto, “Analisis Manajemen Proyek Pembangunan Kantor PT. Prima Multi Usaha Indonesia,†J. Konstr., vol. V, no. 4, pp. 435–445, 2016.

R. Fitrianto and D. T. Sumarningsih, “PENJADWALAN PROYEK KONSTRUKSI DENGAN METODE PENJADWALAN PDM (PRECEDENCE DIAGRAM METHOD) DAN PERHITUNGAN WAKTU DENGAN PERT (PROGRAM EVALUATION AND REVIEW TECHNIQUE) (Studi Kasus : Proyek Pembangunan Gedung TK Sultan Agung-UII Tahap II, Nglanjaran, Sleman),†Univ. Islam Indones., 2016.

N. I. Hayati and D. Lugi, “EVALUASI BIAYA DAN WAKTU DENGAN METODE EARNED VALUE MANAGEMENT (Studi Kasus: Ruko Damara Village, Kel. Ciparigi, Kota Bogor),†J. Komposit, vol. 4, no. 2, p. 61, 2022, doi: 10.32832/komposit.v4i2.3760.

E. Wahyuni and B. Hendrawan, “ANALISIS KINERJA PROYEK ‘Y’MENGGUNAKAN METODE EARNED VALUE MANAGEMENT (Studi Kasus di PT Asian Sealand Engineering),†J. Appl. Bus. Adm., vol. 2, no. 1, pp. 60–78, 2018, doi: 10.30871/jaba.v2i1.784.

I. K. Nudja, “Proyeksi Jadwal dan Biaya pada Pelaksanaan Proyek Pembangunan Atas Jembatan Beton,†Paduraksa, vol. 7, no. 1, pp. 31–40, 2018.

F. Lamato, A. Utiarahman, and M. Y. Tuloli, “Analisis Earned Value Terhadap Proyek Pembangunan Renovasi Gedung Kantor Bpjn,†J. Vokasi Sains dan Teknol., vol. 1, no. 2, pp. 46–53, 2022, doi: 10.56190/jvst.v1i2.10.

A. Purwantoro, K. J. Suhin, and W. Nuswantoro, “PENGENDALIAN PROYEK KONSTRUKSI GEDUNG MENGGUNAKAN CRITICAL PATH METHOD (CPM) DAN EARNED VALUE METHOD (EVM) Krisaverona Janeolantya Suhin,†vol. 5, no. 2, pp. 65–72, 2022.

H. Ryka and I. Hendriyani, “Analisis Kinerja Proyek Pembangunan Siring Sdn 037 Penajam,†vol. 02, pp. 2502–1028, 2016.

I. K. Nudja, “Penjadwalan Kembali Waktu Pelaksanaan Proyek Konstruksi Pada Pembangunan Bangunan Atas Jembatan,†Paduraksa, vol. 7, no. 2, pp. 196–209, 2018.

Diterbitkan
2023-06-30
Bagian
Articles
Abstrak viewed = 95 times
PDF (English) downloaded = 93 times